Which of the following can be root cause of a bug in a software product?

(I) The project had incomplete procedures for configuration management.
(II) The time schedule to develop a certain component was cut.
(III) the specification was unclear
(IV) Use of the code standard was not followed up
(V) The testers were not certified 

a. (I) and (II) are correct
b. (I) through (IV) are correct
c. (III) through (V) are correct
d. (I), (II) and (IV) are correct     